Stay in the Know
Get our insights and latest news straight to your inbox.
Existing General Permits (GPs) are set to expire on December 7, 2024. To maintain coverage, renewal applications must be submitted to the appropriate County Conservation District before this deadline.
Last month, permittees should have been notified of the upcoming expiration by the County Conservation District.
It’s important to note that once a permit expires, it cannot be renewed administratively.
Here are key elements about the process that can help permittees streamline renewals, remain compliant, and strategize erosion control and post construction stormwater management designs moving forward.
To renew a project’s General Permit (GP), two conditions must be reviewed to confirm that the GP still applies:
If the answer to either question is yes, the project is no longer eligible for a GP, and an Individual Permit application will be required.
Bohler can assist in completing this evaluation for your projects.
Post Construction Stormwater Management facilities are now referred to as a Stormwater Control Measures (SCMs). PCSM Best Management Practice or PCSM BMP is no longer used.
To remain compliant under the renewed permit, several new or updated conditions must be met. Below is a summary of these conditions.
If the current Pump Water Filter Bag location is in a non-vegetated area, the team should attempt to relocate it to a vegetated and upland (non-wetland) location to promote infiltration. If such an area is not available, then the discharged water must be treated in a series of two approved Best Management Practices (BMPs). These can include a pump water filter bag and a downslope row of compost filter sock.
This could result in added costs associated with providing the redundant control measures.
If the stormwater management design already includes either the maximum allowable impervious area, or at least 10% greater than the planned impervious area, the permittee would not be responsible for amending the approved PCSM Plan and PAG-02 coverage or documenting future changes on the record drawings.
If these allowances are not incorporated into the initial design, permit modifications will likely be needed for future improvements that create more impervious cover. Bohler’s team can provide an impervious analysis to help navigate this requirement.
A revised version of the Visual Site Inspection Report (VSIR) should be used starting no later than December 8, 2024.
Inspections need to be conducted by a Qualified Site Inspector as outlined below:
The new 4-page form identifies specific elements to be checked and requires the signature of the qualified person completing the inspection. The form can be completed by a licensed professional but is not required to be.
Permittees must take date and time-stamped color photographs of E&S BMPs and PCSM SCMs every month and when deficiencies in BMPs and SCMs are identified. These photographs should be maintained with completed VSIRs.
Effective December 8, 2025, permittees may use only qualified site inspectors to complete the visual site inspections required by the PAG-02 General Permit. There are three options for an inspector to be considered qualified:
There is now a standard PCSM SCM Construction Certification Form. The form includes General Project and SCM Information. Construction information including photographs, deviations from the approved PCSM Plan, measurements to evaluate conformance of the SCMs and its components, and infiltration SCMs testing results are required. Under certain circumstances, infiltration capacity testing will also be required.
A licensed professional must sign and date the Licensed Professional Certification section. Therefore, it is important to incorporate the licensed professional into milestone construction schedules to ensure enough information is available for completing the certification. This may lead to additional costs related to field observations and required documentation.
An annual report on the status of earth disturbance activities must be submitted by December 7th of each year to the DEP/CCD office that approved the general permit coverage. For existing permit holders, the first report is due by December 7, 2025.
Bohler can assist with the preparation of this report. Note that a licensed professional does not need to sign the form.
Any reduction, loss, or failure of BMP or SCM will need to be addressed during construction as follows:
This is not a new requirement, but it now includes more specific time frames in which the repairs are to be completed.
Whenever a lot or parcel containing a PCSM SCM is sold during the term of General Permit coverage, the permittee must provide the new property owner with:
The permittee must submit copies of completed New Property Owner Notification forms to DEP/CCD and to the municipality where the SCM is located within 30 days of the date of transfer of the property.
This is a new requirement that will need to be included in all property transactions.
The DEP must be notified within 24 hours if:
This new requirement may lead to additional costs if laboratory testing is necessary. It could also impact both costs and schedules if any remedial actions are needed.
Beginning December 8, 2025, the permittee must complete confirmation testing for infiltration capacity to verify that infiltration SCMs will perform as designed. Triggers for this testing include when:
Confirmation testing can be completed by 3 optional methods:
A licensed professional must confirm the testing results. If the results are unsatisfactory, the licensed professional will provide guidance on corrective actions. If these actions involve changes to the SCM, a permit amendment may be needed.
This requirement will likely increase costs due to the necessary field testing and will require advance scheduling to ensure testing is done before the relevant construction phase.
Starting December 8, 2024, PAG-02 permittees will no longer need to complete and submit these forms to DEP/CCD for PAG-02 compliance. DEP/CCD will instead monitor operator co-permittees based on changes identified in VSIRs.
This change should result in cost savings, as the form submission will no longer be required.
Once it is confirmed that the General Permit (GP) is still applicable, a complete application must be submitted to the appropriate County Conservation District. The application should include the following items:
Bohler’s design and consulting teams across Pennsylvania are available to provide guidance and to handle submission requirements related to obtaining a NOT or renewal for your existing NPDES General Permit.
This is a fluid situation. We are actively monitoring the renewal process in an effort to empower Bohler’s clients to make well-informed, proactive decisions and stay ahead of potential nonconformities on their sites.
Get our insights and latest news straight to your inbox.